Abpakhsh Sour Gas Compressor Station

Execution of Abpakhsh Sour Gas Compressor Station

Employer: Iran National Gas Company

Consultant: Rohab and Ghods Niroo Consultant Engineers

Contractor: Energy Sazeh Aban

 

Sour Gas (SH2) Compressor Station is located along the sour gas pipeline transport from Asluyeh to Aghajari Oil Well (Nationwide Pipeline Transport no. 5). It is 504 kilometers, beginning in Asaluyeh and passing through Khormuj Compressor Station to Abpakhsh Station and then to Sardasht Station. This project’s operations consisted of infrastructure, pile driving, foundation building, buildings’ metal structure, cable and pipe contraction, construction of service buildings, execution of air conditioning, earthing and etc. The mechanical facilities included installation of turbo-compressors and all auxiliary equipment (air filter, gas cooler, air cooler, air compressor, etc.) and reservoirs.

The piping included execution of all process gas line pipes to a 60 mm width, all utility lines, testing and pre-launching.

This project has been delivered.

 

Project Specifications

No.

Description

Unit

Approximate Quantity

1

Site excavation and transfer

Cubic meter

170.000

2

Embankment at the site

Cubic meter

210.000

3

Pile driving at 20 m, 22 m & 27 m and bentonite usage

Meter length

12.100

4

Reinforcing piles and structures

Kilogram

2.850.000

5

Moulding

Square meter

55.000

6

Connecting plate provision & installation

Kilogram

28.500

7

Provision & execution of concrete with 370 & 385 grades

Cubic meter

25.000

8

Provision & usage of high-performance lubricant

Kilogram

20.000

9

Installation of industrial structures like air coolers, compressor, etc.

Kilogram

3.000.000

10

Sandblasting & painting pipes for sizes up to 56 inches

Square meter

15.000

11

Pipelining for sizes up to 56 inches

Inch diameter

83.000

https://english.energysaze.com/post/11/Abpakhsh-Sour-Gas-Compressor-Station