Execution of 15,000-seat Khorramabad Stadium
Employer: Governmental and Public Buildings and Facilities Executive Organization-Ministry of Roads and Urban Development
Consultant: Iran Arc Consultant Engineers
Contractor: Energy Sazeh Aban
All construction and facility operations of the main and annex building, landscape and access road in an area of 200,000 m2, plus a sports area and parking lot for buses, cars and motorcycles. The main structure was made of concrete, the excavation volume was 450,000 m3 and the embankment volume was 340,000 m3.
All operations regarding reinforcement, mechanical and electrical facilities and lighting towers were carried out by ESA.