Client: Shiraz Urban and Suburban Railway Organization
Consultant: Pol Mir Consulting Engineers
Contractor: Energy Sazeh Aban
Complete execution of all construction works for Ghadir Station, the fifth station on Line 1 of Shiraz Urban and Suburban Railway, consisting of 4 levels with a total floor area of approximately 9,000 square meters.
The structure of this station, designed as a deep station, is entirely concrete and includes:
• 4 entrance gates with an area of 1,200 m² at the pedestrian level (+14 m from rail level)
• Ticket hall level with an area of about 3,000 m² at +6.65 m from rail level
• Platform level with an area of about 1,600 m² at +1.05 m from rail level
• Under-platform level with an area of about 1,600 m² at -1.10 m from rail level
This project has been delivered.